Project & Construction Site

The plant area has been divided into three sectors: the reactor and turbine island, as well as supporting and auxiliary buildings. Illustrations by Fennovoima ja Riina Paakkinen

This is how the Hanhikivi 1 nuclear power plant will be built

The construction of the nuclear power plant takes much more than even the largest industrial plant projects. Approximately 140 buildings will be constructed in the Hanhikivi 1 plant area.

The construction of a nuclear power plant is a huge industrial investment similar to the bioproduct mill in Äänekoski, but the construction of a nuclear power plant will take longer and employ more people than the construction of the large industrial plant.

The construction work in the plant area will start when a construction license based on the Nuclear Energy Act has been granted. During the year after the granting of the license, the number of people working at the construction site will increase to 1,500. At best, some 4,000 people will be simultaneously doing construction and installation work at the construction site, probably during the fourth year after the start of construction.

First, a concrete slab that is several meters thick must be poured. When this has been done, construction of the buildings can be started: the reactor building and the steam generator building, quickly followed by the control room building, the safeguard building, and the turbine building.

The simplified illustration shows the layout and building plan for the Hanhikivi 1 nuclear plant area.​​​​​

Hanhikivi 1 nuclear power area will be built from downwards up

According to the plan, more than a hundred buildings will be constructed side by side in the plant area over the course of five years. The order in which the buildings will be constructed and the schedules in general have been planned with exceptional care.

“The rule of thumb in construction will be proceeding from downwards up and from buildings in the middle of the area to those at the edges. The construction of the buildings that will take the longest to complete will be started early, regardless of their location,” says Petri Jyrälä, Fennovoima’s Engineering Director.

Many factors must be considered in addition to the lack of space in the plant area. Many components will be brought – or lifted into – the buildings while the walls are still being built. Testing of components and systems will also be part of the everyday life of the busy construction site.

“Making sure that all the components to be installed at an early stage are appropriately protected and stored is important to ensure that the components will still be intact and operable at the testing phase,” Jyrälä explains.

The installation work in the reactor building will take five years

When taking into account the preparatory work, installation of the reactor pressure vessel will take approximately one month, but it has been estimated that the mechanical installation work in the reactor building will take almost five years in all. Electrical installation work will take almost four years. In the turbine building, installation of the turbine will take approximately two years and installation of the generator approximately twelve months.

The power plant’s components will arrive as shipments of varying sizes. Most of the components delivered in one piece weigh hundreds of metric tons and can be more than ten meters tall or long.

Components will be delivered by sea to be unloaded at the construction site’s own pier or at ports in the neighboring towns. Most of the building supplies will be transported by road, but plenty of supplies will also be made at the Hanhikivi peninsula. An onsite concrete mixing plant has already been completed, for instance, and a concrete reinforcement plant is currently under construction.

Concrete structures have an important role in building a nuclear power plant

The reactor building is the most demanding structure of the plant area. The casting of the steel-concrete containment alone consists of several inspection phases. Many of the plant area buildings have more stringent strength and other special requirements compared to conventional industrial projects. Concrete has an essential role in the building of the entire nuclear power plant.

The reactor unit will have a thick double-shelled containment building that is several meters thick. The inner containment building made from reinforced concrete will be a prestressed cylinder with an elliptical cover. It has been designed to withstand temperature and pressure loads that may be caused by pipe breaks. The outer containment building will be a reinforced concrete cylinder that provides protection against external hazards.  Both containment buildings will share a base slab.

More than a hundred buildings will be constructed side by side in the plant area over the course of five years.

Preventing release of gaseous material sets extreme requirements on the leaktightness of the containment building, which has an inner liner of steel for this reason. A large number of prestressing cables will be assembled in protection tubes installed inside the concrete wall of the inner containment. Leaktightness of the containment will be monitored, and any leaks will be stopped in the annular space of the containment, i.e. the space between the inner and outer shells of the containment building.

The casting of the concrete shells and the installations of the steel liner and the protection tubes will proceed synchronously from downwards up. This construction phase will be finalized by casting a double dome on the top.

Extensive commissioning phase after testing Hanhikivi 1 nuclear power plant

Testing of the components and systems will start when construction work is still ongoing. The components will be tested first, followed by sub-systems and finally the entire systems. The first commissioning test of the power plant will start before the nuclear fuel has even arrived at the plant. At that time, the construction work will be mostly complete, and there will be a double fence around the plant area and the rest of the site.

When the Radiation and Nuclear Safety Authority (STUK) has given its permit on the basis of the commissioning test results, the fuel will be brought in and loaded into the reactor pressure vessel. This will signal the start of a two-phase nuclear commissioning test. Only after that can the power plant be finally approved and commissioned for regular commercial electricity production.

An interim storage facility for spent nuclear fuel and a final disposal facility for low- and intermediate-level operational waste will be completed later on the Hanhikivi peninsula.

“The rule of thumb in construction will be proceeding from downwards up and from buildings in the middle of the area to those at the edges,” says Petri Jyrälä, Fennovoima’s Engineering Director. Photo by Raisa Ranta

 

Project & Construction Site

Project & Construction Site

Plots from Fennovoima business area now available for lease

The plots in the Fennovoima business area on the Hanhikivi peninsula are now available among the plots for sale in Pyhäjoki. The area has been designed for companies serving the Hanhikivi 1 project or its contractors.

Project & Construction Site

Excellent quality in the nuclear industry

Nuclear industry deliveries are the crown jewels in the reference list of SKM Service from Pattijoki, Finland. For the Hanhikivi 1 construction site, the company has delivered a pumping station.